HS2 Update

 

Wardington Parish Council have received an update regarding the progress of the following HS2 related work. By following the link in 3c more information is available.                                           The following link is a notice of works in your area,Chipping Warden relief road and site compound. RR-Compound_ChippingWarden

 

1.       Road Improvements Wardington and Chipping Warden:

a.       Wardington road improvements are planned to be carried out in autumn.

b.      Chipping Warden Relief Road is due to start in August with the site set up / compound work starting. Please see attached a notification for the works.

2.       U&A regarding engagement relating to Haul Road

a.       Plans to form a haul road along the trace / route of HS2 remain unchanged.

b.      Local traffic management plans are being developed in consultation with the local highways authority and expected to be available in two or three months’ time .  We will share these with you as soon as we are able to.

3.       Other Activities & Engagement

a.       Our Heave trial works near Boddington are expected to start in August as will some further Ground Investigation works.  A site compound for the Ground Investigation is being set up in lower Boddington (the old fir tree nursery site).

b.      We have also been conducting drop ins at Chipping Village Hall with high level plans of Wardington.  A number of residents from Wardington have visited. We will be planning to have more drop ins and will let you know details in due course.

c.       We also have a website which you can subscribe to which gives you further information https://hs2innorthants.commonplace.is/

 

Nisha Mejer | Community Engagement Manager Phase One C3 | HS2 Ltd